Most winter plans for commercial properties are written around a single storm.
They set out how much snow triggers a visit, which areas are cleared first and how quickly the work has to be done. Those are the right things to settle, and in most winters they are enough.
Last January in Toronto, they were not.
Two major snow events, declared on January 15 and January 25, brought about 90 centimetres of snow in ten days.
The City's annual winter maintenance report, which went to its Infrastructure and Environment Committee in May, is a candid account of what happens to a large, well-resourced operation when storms arrive faster than the snow can be moved.
What the City found
Over 39 days, Toronto hauled away about 538,000 tonnes of snow, more than double the 253,000 tonnes removed after the storms of February 2025. Its five permanent snow storage sites, in the report's words, "reached or approached capacity." Trucks had to travel farther to find room, which slowed the work behind them, and two temporary sites were added afterwards. The hauling contractor supplied roughly 700 trucks against a contracted 480, and about 250 staff were redeployed from six other City divisions.
Among the improvements the report identifies is one that applies to every commercial property in the country: "clearer thresholds for transitioning from snow clearing to snow removal."
The same problem on a smaller site
Clearing and removal are different jobs. Clearing pushes snow to the edge of a lot. Removal loads it onto trucks and takes it somewhere else. Most contracts price the first and treat the second as an extra, approved one request at a time. That arrangement holds until the piles from one storm are still standing when the next one arrives.
On a commercial site, the consequences are easy to recognize. Parking spaces disappear under the piles. Sight lines at the exits narrow. Meltwater runs across a walkway during the day and freezes overnight. A loading area that had room for a trailer to turn no longer does. The plowing may have been done exactly as the contract asked. What was missing was a decision about where the snow would go next, and who had the authority to make it.
Three questions for this winter's plan
The first is capacity. Every site can hold a certain amount of snow before it starts to give up parking, access or drainage, and that amount can be estimated on a site walk in the fall. Few plans record it.
The second is the trigger. Someone has to decide when clearing becomes removal, and the middle of a second storm is a poor time to look for that person. A plan can name the threshold, the rate and the approval in advance, so the decision takes one call.
The third is where the trucks and the space will come from. Toronto found 700 trucks because its contractor could supply them. A commercial site has no such claim on anyone unless it was arranged before the season. The rules also change from one city to the next. In Ottawa, for example, the City states that its snow disposal facilities do not accept snow from private operators, so a property there depends entirely on private capacity. A national portfolio has as many answers to this question as it has municipalities.
What it costs to plan for the second storm
There is a fair objection to all of this. Last January was exceptional, and reserving trucks and storage for a winter that may not come is money spent on a risk that may not arrive.
Most of the planning costs very little. Measuring what a site can hold and agreeing on who approves removal takes a conversation and a walk. Where capacity does have to be reserved, an owner can decide which properties justify it: a hospital, a distribution centre or a residential building where access cannot wait is a different case from a suburban office with spare parking.
The alternative is to negotiate during the storm, when every property in the region is calling the same trucks.
The question to put to any winter plan this month is a simple one: after the first big storm, how much room does this site have left?