GUEST SUBMISSION: Most renovation budgets for older commercial buildings are set before anyone looks inside the walls. On paper, the numbers work. Then the work starts, and the building shows you what it really needs.
I own a general contracting company in B.C. A lot of our work is renovating older commercial spaces for new tenants. We see the same thing again and again.
The plan made sense. The design was good. But no one knew what was hidden behind the walls and ceilings.
When we find these problems, it's usually too late to plan for them. A tenant is waiting to move in. The permit is already with the city. The bank is watching the schedule.
Every change at that point costs more time and more money.
Same problems tend to crop up
The good news is that most of these problems are easy to predict. In older buildings, we see the same ones over and over.
The problems we see most:
- Not enough power: Many older buildings were built for basic offices. A restaurant, a clinic or a busy modern office needs much more power. So do EV chargers. Getting more power from the utility can take months.
- Old heating and cooling: The rooftop units are often old and close to failing. They may not bring in enough fresh air for the new use. Sometimes the roof has to be checked before it can hold new equipment.
- Old plumbing: Pipes may be worn out. There may not be enough washrooms for more people. A restaurant may need a grease trap that no one planned for. In a building on a concrete slab, moving a washroom can mean cutting into the floor.
- Gaps in fire walls: After years of renovations, fire walls often have holes that were never sealed. Some walls stop at the ceiling instead of going all the way up. Fixing this, or adding sprinklers and alarms, can cost more than expected.
- Accessibility: New work may need to meet today's accessibility rules. Steps at the front door and small washrooms are hard to change.
- Asbestos: Many buildings from before the 1990s still have it, in drywall, floor tiles and pipe wrap. In B.C., the building must be tested before the renovation starts, and any asbestos must be removed first. That adds cost and time.
- Wrong drawings: Old drawings often don't match the building. Sometimes there are no drawings at all.
None of this means the building is a bad buy. It just means the budget should include these costs from the start.
Finding problems late costs the most
Each of these problems costs money to fix. But the bigger cost is finding them too late.
If we find a problem in the middle of construction, the work stops. The plans may need to change. The permit may need to be updated. The tenant's move-in date gets pushed back. Meanwhile, the owner keeps paying for a building that isn't earning rent.
If we find the same problem before the building is bought or the lease is signed, it's simply part of the plan. The owner can budget for it, negotiate the price, or choose a different tenant.
How to check early
This doesn't need to be a big job. A few days is often enough.
- Walk through the building with a contractor, and with engineers if the use is changing.
- Check how much power the building has and how old the rooftop units are.
- Open a few small holes in walls and ceilings to see what's inside.
- Test for asbestos early.
- Find out which building code rules the new use will bring in.
- Ask the city how long permits are taking.
- Ask for a budget that shows the risks, not just one number.
This costs very little compared to the renovation itself. It's most useful before you buy or sign, when you still have room to negotiate.
Talk to a builder sooner
Most buyers get a building inspection report. It tells you what is in the building today. It doesn't tell you what it will take to turn the space into what you need.
The people who will open the walls are the best ones to answer that question. Bring them in early, even just for a walk-through. With older buildings, that one step can be the difference between a project that stays on budget and one that doesn't.